Xcel Energy contracted MHI to perform a Switching Surge Study on Chisago 34.5 kV Station.

Manitoba Hydro International Ltd. (MHI) provided the following services:

  • Calculated maximum line-to-ground and phase-to-phase over-voltage data to which nearby radial-fed transformers may be subjected
  • Determined the expected energy absorption requirements of 115 kV lightning arresters for worst case capacitor energization at Chisago
  • Determined an appropriate in-rush/out-rush reactor design for the new shunt capacitor banks at Chisago
  • Determined if there is any possibility of voltage magnification on nearby capacitor banks as a result of adding the Chisago capacitors.
  • Confirmed the suitability of capacitive switching ratings of new and existing 115 kV circuit breakers that may be required to switch the Chisago capacitors.
  • 0

Manitoba Hydro International Ltd. 211 Commerce Drive Winnipeg, Manitoba, Canada R3P 1A3

Eric Maxwell Marketing Manager Direct: 1 (204) 480-5585 E-mail: emaxwell@mhi.ca